"reload system power-cycle" command is missing in SLOX OS 18r100d release

« Go Back

Information

 
Title"reload system power-cycle" command is missing in SLOX OS 18r100d release
Symptoms
SLX# reload system ?
Possible completions:
    standby      Reboots the standby MM
  |            Output modifiers
  <cr>

 
Environment
  • CLI
  • SLX  9850
  • SLX OS 18r100d
Cause
FPGA upgrade process needs 30 second power outage and this is not possible with the CLI command.
'reload system <power-cycle>’ option has been deprecated 
Now the ‘reload system <cr>’ alone will power-cycle the system except the SFM modules

 
Resolution
Power cycle the modules by removing power to the entire chassis(Perform either option a or b).
        A.   If the chassis has the PDU(Power-supply/tower connection to the chassis), disable the power connections to the chassis for 30 seconds (No active Power supplies or modules). Enable the power connections 
        B.    Alternatively, physically remove all power cables to the device, wait for 30 once the last cable is removed, and insert all the power cables into the device.

 
Additional notes
Extreme Networks will address power-cycling  the system including  the SFM modules in a future release